Pak Chong Tunnel Collapse: Investigation Launched After Tragic Incident Kills 3 Workers
Photo: State Railway of Thailand NAKHON RATCHASIMA: Last Thursday was marked by a somber scene as ambulances lined the entrance of the railway tunnel in Pak Chong district. This came in the wake of a tragic incident…


Photo: State Railway of Thailand
NAKHON RATCHASIMA: Last Thursday was marked by a somber scene as ambulances lined the entrance of the railway tunnel in Pak Chong district. This came in the wake of a tragic incident that claimed the lives of three workers. Now, a dedicated team of investigators has been appointed to scrutinize every aspect of the tunnel collapse. Their mission: to understand what went wrong and, more importantly, ensure it never happens again.
According to Pol Col Veerapol Rabiappho, the superintendent of Pak Chong police station, the investigation will be thorough and multifaceted. “Our aim is to interview all relevant parties,” he explained. This includes workers on site, the contractor, and representatives from esteemed organizations such as the Council of Engineers, the Engineering Council of Thailand (ECO), and the Engineering Institute of Thailand (EIT).
Rigorous examination of the findings from the State Railway of Thailand (SRT) will play a crucial role in the investigation. Police are set to delve deep into whether the construction adhered to the original design, regulatory requisites, and paramount safety standards. However, Pol Col Veerapol cautioned that the investigation would be painstakingly detailed and, thus, time-consuming.
In light of the incident, all construction activities within the tunnel have been suspended. Discussions are now in progress among engineers and the contractor to decide how best to proceed while ensuring the supreme safety of all involved.
The tragedy unfolded in the night hours of August 27, following heavy rainfall that battered the region for days. The victims—two Chinese nationals and one from Myanmar—were working roughly 1.5 kilometers from the tunnel’s entrance when the structure gave way. The tunnel itself stretches four kilometers, leading to Khlong Khanan Chit station in Pak Chong district.
A grueling search and rescue operation ensued. While the first body was recovered last Thursday, it took until Friday to recover the remaining two. The ongoing rail construction and harsh working conditions significantly hindered rescue efforts.
Suchatvee Suwansawat, a recognized authority in tunnel and underground construction, has called for this incident to serve as an important lesson. “Every agency involved in complex construction projects must take heed,” he emphasized. Each construction site is unique, with varying soil and rock conditions that necessitate specialized equipment and expertise.
“The method employed for this rail tunnel was known as ‘drill and blast,’” Suchatvee elaborated. Although this technique is considered less safe compared to the more high-tech boring machine method, it remains widely used due to its cost efficiency. Under the right circumstances—with top-notch design, appropriate construction equipment, and stringent safety measures—it can still be executed safely.
Suchatvee, who also serves as a deputy leader in the Democrat Party, stressed the importance of advancing safety protocols and practicing vigilance in construction management. “Budget constraints should never justify compromising safety,” he said.
As the investigative team dives deeper into the cause of the collapse, the hope is that enhanced safety measures will not only honor the lives lost but also pave the way for safer future projects. The lessons learned from this tragic event aim to foster a culture of safety, innovation, and responsibility in Thailand’s growing infrastructure landscape.



Comment verification
Step 1 of 3
Verify your email once to publish your comment. Your email is never shown publicly.
Enter the 6-digit code sent to .
Choose the display name shown next to your comments.