Reviving Pattaya’s Eastern Region National Sports Complex: 774 Million Baht Venture Awaits Grand Finale by December 2025

The grand vision of making Pattaya a national sports hub has been sitting on the sidelines since 2008, gathering not fans but layers of neglect. This grand enterprise, a whopping 774 million baht ambition, unfurls across 59 hectares in the heart of Chon Buri like an unfinished epic tale. Destined to become a stage for international events, it now paints a rather forlorn picture, more of a ghost town than a bustling arena.

Just yesterday, the complex was back in the spotlight with an inspection by Thailand’s National Anti-Corruption Commission (NACC), spearheaded by the ever-vigilant Saroj Phueng-ramphan. The scene that greeted the commission was not one of victory but of vacant promise—a 20,000-seat capacity monument to dreams deferred. What was meant to captivate the world now pleads for redemption under the weight of damaged equipment and neglected facilities.

In a bid to piece together this ambitious jigsaw, Boonthian Jansuk, Director of Pattaya’s Engineering Office, presented an update that was as colorful as a weather report—a mélange of delays, expectations, and technical conundrums. Repairs, it seems, have become the team’s middle name, with tasks like untangling electrical systems, touching up the faded seats, and juggling fire alarms that seem to have their own agenda.

The complex’s unfinished grandstand bears witness to what’s turning out to be a saga of epic delays. Workers, like determined ants, tackle the incomplete steel roof structures and faulty ramps, braving setbacks from stubborn drainage systems and machinery that perhaps belong in a museum. While they aim for a December finish line, setbacks point towards further delays—ironic, given December seems to feel like a deadline marathon.

The NACC’s keen interest in this halted project isn’t born purely out of an affinity for sports. Dismal progress and unspent public funds have transformed the complex into a puzzle begging to be solved. Saroj candidly pointed out that the blame game lands squarely on contractor inefficiencies coupled with curveballs thrown by the infamous COVID-19 pandemic, setting the stage for a dramatic, albeit frustrating, series of events.

Since 2023, efforts to breathe life into this sleeping giant have been like a relay race that doesn’t quite end. Collaboration with local authorities, contractors, and private stakeholders is nudging the project towards its dream date of December 2025. By then, hopefully, only minor details like landscaping and seating will stand between the complex and its grand awakening.

The NACC’s probe bravely trudges on, not from a need to hunt down corruption but to uphold integrity—an Olympic-level challenge on its own. Pattaya Mayor Poramet Ngampichet is already strategizing post-completion playbooks to maintain the complex as a beacon for both competitions and sweaty training sessions, preparing for a future that’s as bright as the blazing Thai sun.

Besides the sports drama, the inspection also took a detour to Soi Thepprasit 9, where an unfinished drainage system lurks as a separate budget-behemoth of 190 million baht. Road closures echo the silent promises of an incomplete saga, limiting access to an infrastructure story tinged with irony and urgency.

As the NACC digs deep into this epic, unraveling layers of delays and shining a light on both missed targets and hopeful plans, Pattaya’s dreams are poised on the brink. With a bit of elbow grease and perhaps a dash of luck, the Eastern Region National Sports Complex might just reclaim its throne as a grand stage where greatness struts and potential no longer languishes as an untold story.

29 Comments

  1. Lisa M June 27, 2025

    774 million baht and still not finished? The amount of money wasted is astounding.

    • Victor June 27, 2025

      Corruption is a real issue in Thailand, isn’t it? Makes you wonder where all that money really went.

      • Lisa M June 27, 2025

        Exactly, Victor. It’s always the taxpayers who end up paying for these mistakes.

      • SportLover77 June 27, 2025

        But isn’t it about time someone held these people accountable? We need the NACC to do a thorough investigation.

    • VisionaryPat June 27, 2025

      Don’t forget the delays caused by COVID-19; let’s give them some credit for that.

  2. goofy123 June 27, 2025

    I bet by 2025, they’ll be asking for more money. These projects never end without additional funds.

  3. Athena Grace June 27, 2025

    It’s a shame how such a potentially great asset for sports and events is left wasted.

    • Joe June 27, 2025

      Maybe once it’s completed, the revenue from events can help recover some of the costs?

      • Athena Grace June 27, 2025

        True, Joe. But the longer it stays unfinished, the less likely it is to ever be profitable.

  4. TechieMike June 27, 2025

    Technical failures are rampant—imagine untangling all those electrical systems!

    • Sarah Potts June 27, 2025

      And what about the safety risks involved with faulty equipment? It’s a disaster waiting to happen.

      • TechieMike June 27, 2025

        My thoughts exactly, Sarah. A rush to meet deadlines usually compromises safety.

  5. runnergirl June 27, 2025

    If the sports complex ever gets finished, it could be a fantastic addition to Pattaya.

  6. Ben Observer June 27, 2025

    Is anyone surprised that the unfinished drainage system is still brewing problems?

    • Chris Bale June 27, 2025

      Nope, that’s just typical bureaucratic mess-ups for you.

      • Ben Observer June 27, 2025

        I just hope it’s actually fixed before it causes more issues.

  7. JK47 June 27, 2025

    Sounds like a scene from a nightmare for the contractors involved. How do they work under so much pressure?

    • Diane L. June 27, 2025

      Pressure is a part of their job, but it’s still no excuse for inefficiency.

  8. Mohammed N. June 27, 2025

    Good luck seeing this project become a reality by the estimated deadline.

  9. SkepticSue June 27, 2025

    Another unfinished Thai urban legend in the making! Will it ever end, I wonder?

    • CheeryChad June 27, 2025

      Think positive, Sue! They’ll eventually pull through!

      • SkepticSue June 27, 2025

        I’ll believe it when I see it, Chad.

  10. FieldGuy June 27, 2025

    They need a better plan, hiring new contractors might be a start.

    • ProjectWisdom June 27, 2025

      New contractors come with new problems, potentially even more delays.

      • FieldGuy June 27, 2025

        True, but any change could be better than the current situation.

  11. Anna K June 27, 2025

    Enough with all the negativity. Let’s focus on the complex’s potential as a sports hub!

  12. plumberJay June 27, 2025

    With the drainage mess, the only thing flooding will be their mailbox with complaints!

  13. quietqueen June 27, 2025

    It might take forever, but at least the NACC is keeping an eye on it.

  14. eventhunter June 27, 2025

    I’m optimistic. A December 2025 opening is ambitious, but definitely possible.

Leave a Reply to goofy123 Cancel reply

Your email address will not be published. Required fields are marked *

More from ThailandMore posts in Thailand »