Phuket Expressway and Tram Stuck After 10 Years
After more than ten years of studies, Phuket's Kathu-Patong expressway and airport light rail are still unbuilt, and high-season traffic is already leaving visitors short of flights.

Phuket's high season is stacking cars on the two roads that carry the island, and the projects meant to relieve them are still files. On 28 November 2026, Democrat deputy spokesperson Duangruthai Buakaew told the government and the Transport Ministry that visitors are missing flights, that patchwork road works have not ended the jams, and that both the expressway and the rail scheme have been studied for more than ten years without a construction start.
She asked the ministry to pick one technology, a rubber-tyred system or light rail, and to connect it to Phuket International Airport. She also asked for the southern railway, which still ends at Surat Thani, to reach the island, and she told the transport minister that a decade was long enough to say what will actually be built.
Two expressway phases, and no contractor
The Expressway Authority of Thailand has split the scheme into 34.60 kilometres. Phase 1, Kathu to Patong, is 3.98 kilometres of elevated road and twin tunnels through Khao Nak Kerd on Phra Baramee Road, Highway 4029. Phase 2 runs 30.62 kilometres from Muang Mai through Koh Kaew to Kathu, along Thep Krasattri Road, Highway 402, the airport-to-town spine.
Private money has already refused the first phase. The partnership tender under the 2019 PPP Act drew no bidder. EXAT took a revised approach to its board on 23 November 2023 and to the ministry on 23 February 2024, then had consultants review the project from 28 June 2024 to 23 April 2025. That review put the economic return at 18.85 percent and the financial return at 1.82 percent.
In September 2026, with a plan to raise about 20 billion baht for Phase 1, Kathu-Patong was priced at 16.757 billion baht, with 5.792 billion for land and 10.965 billion for construction and supervision. The timetable then showed cabinet consideration in December 2026, construction in October 2027 and an opening in October 2031. Phase 2 was priced at 46.752 billion baht, with 22.012 billion for land and 24.740 billion for works, a cabinet date of September 2027, construction in October 2028 and the same October 2031 opening.
That opening year has already moved. On 27 November 2026 the government publicity briefing at EXAT's 54th anniversary set 2032 for both phases. The same day Transport Minister Pipat Ratchakitprakarn said Kathu-Patong, still 3.98 kilometres and 16,757 million baht, has been in the cabinet process since August 2026, with construction hoped for in 2027. Nothing in either briefing says a contractor is on site.
The airport tram is still a review
The Mass Rapid Transit Authority still lists the line as a low-floor light rail, not a signed contract. The alignment runs 42.0 kilometres from Phuket International Airport to the Chalong five-way intersection, with 21 stations. One is elevated, one underground and 19 at ground level, with about 3 kilometres of tunnel in Thalang.
An October 2020 partnership summary on that page puts the economic return at 13.11 percent, the financial return at 2.34 percent, and opening-day ridership near 39,000 trips. The schedule beside it has cabinet approval in February 2028, construction in September 2029 and operations in December 2032. The status line underneath has not moved: the authority is reviewing the feasibility study and preparing the PPP report.
The published specification is already a tram, yet the technology is still described as something that changes with the minister. A January 2015 public hearing was already discussing a light rail that might open around 2021. Until one design is locked to the airport, December 2032 is a planning date, not a service.
High season is already past the airport's design
Phuket International Airport handled 17,234,915 passengers in fiscal 2026, October 2025 through September 2026, on 105,010 flights. Director Karant Thanakuljeerapat put the daily average near 47,219 passengers and 288 flights, against a design capacity of 12.5 million a year. The winter schedule, 25 October 2026 to 27 March 2027, is forecast at 54,296 flights and 8,912,547 passengers.
The Tourism Authority of Thailand's Phuket office counted 10.25 million visitors from January through September 2026, down 1.6 percent, and 399.96 billion baht in revenue. Without a car, travelers are left with songthaews, ride-hailing and taxis.
What This Means for Expats and Travelers in Thailand
Treat 2026 and 2027 as a no-project window. Neither the Kathu-Patong tunnels nor the airport tram will carry a passenger this high season or the next. An evening flight from Patong, Karon, Kata or Rawai still needs a buffer of hours. A Rawai-to-airport run on 26 December 2025 left at 7:10pm and reached the terminal at 9:10pm.
Morning departures are the safer booking. The SMART bus from Bangla Road is about 100 baht and roughly hourly, a poor fit for a fixed check-in. A direct taxi from Patong is commonly budgeted around 1,500 baht and an hour to an hour and a half when the road is moving.
The expressway is further along than the tram: a failed private tender, a review closed in April 2025, published budgets, and a cabinet file ministers say has been live since August 2026. The tram is still, on MRTA's own page, a feasibility review. A 2032 opening for both means Phuket spends the rest of this decade on the roads it has.