Bangkok Counters Critics With Phuket Expressway Data

Thailand's government published updated EXAT progress figures on the 84.2-billion-baht Phuket Expressway to rebut Democrat Party claims of stalled island infrastructure.

Bangkok Counters Critics With Phuket Expressway Data
Bangkok Counters Critics With Phuket Expressway DataIllustration: THAI.NEWS

Thailand's government pushed back on 29 November 2026 against opposition claims that it has neglected Phuket's worsening road gridlock. Deputy Government Spokesperson Ploytalay Laksameesangchan released updated Transport Ministry and Expressway Authority of Thailand (EXAT) milestones for the two-phase Phuket Expressway, directly answering Democrat Party Deputy Spokesperson Duangruethai Buakaew. The opposition had faulted the Transport Ministry for decade-long delays as severe jams on the resort island leave tourists stranded on the way to Phuket International Airport.

Government House framed the dispute as a clash between political impatience and statutory due process. Large transport works affecting thousands of landowners require environmental clearances, forestry permits, and sovereign financing sign-offs before excavators can roll. Yet the official timetable also confirms a sobering reality for residents and hoteliers: even if every milestone holds, drivers will wait until October 2031 for relief.

The Kathu to Patong Tunnel by the Numbers

The administration's defense rests primarily on Phase 1, the 3.98-kilometer Kathu to Patong link designed to bypass the steep, accident-prone switchbacks of Phra Barami Road on Highway 4029. Official figures released on 29 November show land expropriation reached 99.52 percent by September 2026, with forestry land-use approval already secured. The Transport Ministry is preparing to place the revised project dossier before the Cabinet in December 2026.

EXAT's internal schedule leaves little margin for slippage. Land acquisition is slated to close in January 2027, followed by contractor selection in April 2027 and groundbreaking in October 2027. A four-year build would open the corridor in October 2031. Engineers trimmed the width of the 1.85-kilometer twin-bore tunnel through Khao Nakkerd from 17.1 meters to 14.2 meters to contain material costs, reflect geological findings, and meet seismic standards. Once open, the tunnel will cut the Kathu to Patong crossing from roughly 30 minutes to five minutes and trim the wider cross-island route by seven kilometers, from 35 kilometers to 28 kilometers.

Financing Shifts and Toll Economics

The tunnel's prolonged gestation reflects finance as much as geology. Earlier attempts to attract private consortia under a full public-private partnership stalled because bidders balked at tunneling risk and high upfront capital outlays. To break the logjam, EXAT pivoted toward state-backed funding. The State Enterprise Policy Office is assembling a 60 to 70 billion baht Infrastructure Fund across multiple state agencies, from which EXAT plans to raise about 20 billion baht for Phase 1.

Affordability also forced a rethink of user charges. Unusually for a Thai expressway, the four-lane Khao Nakkerd tunnel will include barrier-separated lanes for motorcycles alongside four-wheel traffic. EXAT lowered projected tolls to 10 baht for motorbikes and 20 baht for passenger cars, scaling up to 60 baht for heavy trucks. Even at those reduced tariffs, EXAT projects daily revenue of 960,000 baht and an economic internal rate of return of 19.47 percent, buoyed by fuel savings and fewer hill-road crashes.

Phase Two and the North-South Bottleneck

Critics still hold a strong hand on one point: Phase 1 alone will not cure the jams that make tourists miss flights. Airport traffic crawls down Highway 402, Thep Krasattri Road, which carries almost all north-south freight and passenger volume across the island. Relieving that spine depends on Phase 2, a 30.62-kilometer expressway linking Mueang Mai near the airport through Koh Kaew down to Kathu.

Phase 2 carries an estimated direct capital cost of 46.75 billion baht, exceeding 1.5 billion baht per kilometer, split between 22.01 billion baht for land acquisition and 24.74 billion baht for construction and supervision. Its environmental impact assessment cleared approval on 18 December 2025, and EXAT is now pursuing forestry and Agricultural Land Reform Office land-use clearances. Cabinet submission for Phase 2 is targeted for September 2027, with construction slated for October 2028 so both sections and a joint private operations concession can open together in October 2031.

What This Means for Expats in Thailand

Phuket's large foreign resident community and tourism operators face five more years of interim pressure before concrete relief arrives:

  • Plan Larger Airport Buffers Through 2031: Highway 402 will remain the primary artery between northern Phuket and southern beaches until Phase 2 opens. High-season transfers from Patong, Kata, or Rawai to Phuket International Airport still require two to three hours during peak afternoon windows.
  • Safer Motorbike Access Across Patong Hill: Unlike Bangkok's expressways, the Kathu to Patong tunnel will permit motorcycles in dedicated barrier-separated lanes for a 10-baht toll, removing riders from monsoon landslides and brake-failure hazards on Phra Barami Road.
  • Property and Rental Repricing: Land acquisition completion around Kathu and upcoming corridor clearances along Koh Kaew and Mueang Mai are already lifting land values near planned interchanges, likely tightening long-term rental budgets for expats working in central Phuket.
  • Watch the December 2026 Cabinet Vote: Approval next month is the critical gate for the April 2027 tender. Any further redesign or financing delay will push the October 2031 opening date deeper into the next decade.
Topics:Phuket Tourism, Transit & InfrastructureSuvarnabhumi Airport & Thai Aviation
3Comments
Sort by:
GWGraham Whitaker··1 pts · 1 reply
GW
Graham Whitaker
I have lived in Kathu since 2014 and heard the Patong tunnel was starting next year at least six times. Getting land acquisition to 99.52 percent is genuine progress, though October 2031 still feels a lifetime away when you sit on Phra Barami Road in the rain.
1
MLMartin Lindqvist··1 pts
ML
Martin Lindqvist
Spot on Graham. The real test is April 2027. If no construction consortium bids at the revised 10.9 billion baht civil works ceiling, the whole calendar slides back two years again.
1
SLSomchai Limpakarn··1 pts
SL
Somchai Limpakarn
Land acquisition reaching 99.52 percent is not easy in Phuket where land prices are sky high. Let us hope the Cabinet actually signs off in December without another study.
1